September 2001 |
|
Shortly after we started |
|
|
|
|
|
|
|
|
|
|
September 2001 |
|
2 weeks into the project |
|
|
|
|
|
|
|
|
|
|
|
November 2001 |
|
New floor laid |
|
|
|
|
|
|
|
|
|
|
11th November 2001 |
|
Floor completed |
|
|
|
|
|
|
|
|
|
|
|
25th November 2001 |
|
Stud work starts |
|
|
|
|
|
|
|
|
|
|
|
27thy November 2001 |
|
More stud work |
|
|
|
|
|
|
|
|
|
|
8th January 2002 |
|
Plaster board up at last! |
|
|
|
|
|
|
|
|
|
|
|
14th January 2002 |
|
More stud work completed |
|
|
|
|
|
|
|
|
|
|
14th January 2002 |
|
Internal wall done |
|
|
|
|
|
|
|
|
|
|
27th January 2002 |
|
Stairs are in. |
|
|
|
|
|
|
|
|
|
|
27th January 2002 |
|
Plastering underway |
|
|
|
|
|
|
|
|
|
|
2nd February 2002 |
|
All stairs installed |
|
|
|
|
|
|
|
|
|
|
10th February 2002 |
|
Plastering done and painting starts |
|
|
|
|
|
|
|
|
|
|
5th March 2002 |
|
We're in! But still loads to do. |
|
|
|
|
|
|
|
|
|
|
20th May 2002 |
|
Aurthur fits the stair banisters |
|
|
|
|
|
|
|
|
|
|
20th May 2002 |
|
Stairs with banisters |
|
|
|
|
|
|
|
|
|
|
2nd July 2002 |
|
Stairs finally completed |
|
|
|
|
|
|
|
|
|
|
1st August 2002 |
|
11 months on and finally we have a carpet in the dinning room. |
|
|
|
|
|
|
|
|
|
|
1st August 2002 |
|
Dinning room with carpet |
|
|
|
|
|
|